Learn what to expect when your meter will be changed. More Information
The timeline may change during construction
June 2020
Notice to Proceed
June 2020
July-August 2020
Material procurement and mobilization
August 2020
Water Meter Installations to begin
August 2020
August 20, 2020 – December 5, 2020
MUD 39
September 9, 2020 – December 15, 2020
MUD 1
September 9, 2020 – December 15, 2020
October 26, 2020 – January 8, 2021
MUD 7
December 9, 2020 – March 17, 2021
MUD 67
December 9, 2020 – March 17, 2021
February 4, 2021 – April 30, 2021
MUD 60
April 12, 2021 – July 23, 2021
MUD 47
April 12, 2021 – July 23, 2021
July 12, 2021 – October 22, 2021
MUD 46
October 4, 2021 – October 29, 2021
METRO
October 4, 2021 – October 29, 2021
October 18, 2021 – November 12, 2021
MUD 6
November 1, 2021 – December 3, 2021
MUD 36
November 1, 2021 – December 3, 2021